Home / Taylor County / Project

Crusoe Abilene AI factory for Microsoft (adjacent campus)

Crusoe; Microsoft (customer)

Status
Under construction
Developer / parties
Crusoe; Microsoft (customer)
Location
Abilene, Taylor County
Size
900 MW site incl. 900 MW behind-the-meter on-site power plant + BESS; 2 buildings × 336 MW critical IT (Crusoe; DCD reports Microsoft lease of 900 MW capacity)
Last verified
2026-10-03

Milestones

Figures are attributed in parentheses to the outlet or company that reported them. Where sources disagree, we show both.

  1. Mar 27 2026 announced, land clearing/site prep underway (Crusoe; DCD)
  2. first building expected to energize mid-2027 (Crusoe; DCD)

Related records

2026-03-27
Company announcement Company claim Taylor County · Crusoe Abilene AI factory for Microsoft (adjacent campus)

Crusoe announces 900 MW AI factory campus in Abilene for Microsoft.

Source: crusoe.ai ↗

Sources

Found an error? Email support@txdatacenterwatch.com with a source link.

Free weekly digest

One email a week: new filings, votes, hearings and comment deadlines in Texas data center and power projects, each with its source. No spam, unsubscribe any time.

TODO (launch): signup endpoint not connected. Submissions are not stored yet.