Home / Taylor County / Project
Crusoe Abilene AI factory for Microsoft (adjacent campus)
Crusoe; Microsoft (customer)
- Status
- Under construction
- Developer / parties
- Crusoe; Microsoft (customer)
- Location
- Abilene, Taylor County
- Size
- 900 MW site incl. 900 MW behind-the-meter on-site power plant + BESS; 2 buildings × 336 MW critical IT (Crusoe; DCD reports Microsoft lease of 900 MW capacity)
- Last verified
- 2026-10-03
Milestones
- Mar 27 2026 announced, land clearing/site prep underway (Crusoe; DCD)
- first building expected to energize mid-2027 (Crusoe; DCD)
Related records
2026-03-27
Company announcement Company claim
Crusoe announces 900 MW AI factory campus in Abilene for Microsoft.
Source: crusoe.ai ↗Sources
- Company claim crusoe.ai
- News report datacenterdynamics.com