Home / Carson County / Project

Project Matador (HyperGrid campus)

Fermi America

Status
In development
Developer / parties
Fermi America
Location
Amarillo area, Carson County
Size
4 proposed AP1000 reactors under NRC review; reactors 'would provide 4 GWs' of baseload power and campus may include ~11 GW total generation and up to 30M sq ft of computing space (NRC, Federal Register); four AP1000s 'totalling 4.4 GWe' within a planned 17 GWe campus (NEI Magazine, citing Fermi); first Siemens Energy gas turbines arrived on site (Fermi, via CRO)
Last verified
2026-10-03

Milestones

Figures are attributed in parentheses to the outlet or company that reported them. Where sources disagree, we show both.

  1. Jun 17 2025 COL application initial submittal
  2. Sep 5 2025 NRC acceptance letter
  3. Mar 20 2026 NRC notice of intent to prepare EIS, scoping comments due Apr 20 2026 (Federal Register)
  4. Sep 28 2026 NAES selected to operate gas turbine fleet (CRO)
  5. nuclear construction slated to begin 2031 (NEI Magazine, Mar 17 2026). Current NRC docket status not re-checked: nrc.gov blocked our fetchers

Related records

2026-03-20
Federal filing Official record Carson County · Project Matador (HyperGrid campus)

Federal Register: NRC intends to prepare EIS for Fermi America's four-unit AP1000 COL application; scoping comments due Apr 20 2026.

Source: govinfo.gov ↗

Sources

Found an error? Email support@txdatacenterwatch.com with a source link.

Free weekly digest

One email a week: new filings, votes, hearings and comment deadlines in Texas data center and power projects, each with its source. No spam, unsubscribe any time.

TODO (launch): signup endpoint not connected. Submissions are not stored yet.