- Status
- Under construction
- Developer / parties
- Crusoe; Google
- Location
- Claude area, Armstrong County
- Size
- Gigawatt-scale campus; 933 MW off-grid gas turbines; 265.5 MW Goodnight Wind farm (Latitude Media)
- Investment
- Part of Google's $40B Texas investment; Buildings 3 and 4 est. $500M each (TDLR filings via DCD)
- Concerns / impacts
- Off-grid gas generation (Latitude Media)
- Last verified
- 2026-10-03
Milestones
- Nov 2025 Armstrong County campus announced by Google
- Jul 30 2026 Crusoe filed for Buildings 3 and 4
- phased go-live Aug 2026–Feb 2027 (DCD)
Related records
2026-07-30
News News report
DCD: Crusoe files for Goodnight Campus Buildings 3 and 4, est. $500M each; phased go-live Aug 2026–Feb 2027.
Source: datacenterdynamics.com ↗Sources
- News report datacenterdynamics.com
- News report latitudemedia.com
- Company claim blog.google