Vantage TX12 (TX1 campus)

Vantage Data Centers

Status
Registered (TDLR status: Review Complete)
Developer / parties
Vantage Data Centers
Location
San Antonio, Bexar County
Size
Up to 96 MW critical IT; 432,800 sq ft
Investment
Est. cost $276.9M (TDLR TABS)
Last verified
2026-10-03

Milestones

Figures are attributed in parentheses to the outlet or company that reported them. Where sources disagree, we show both.

  1. Sep 18 2025 TDLR registration
  2. start Oct 14 2025
  3. completion Aug 31 2027

Related records

2025-09-18
Building registration (TDLR) Official record Bexar County · Vantage TX12 (TX1 campus)

TDLR TABS: Vantage TX12, up to 96 MW IT, 432,800 sq ft, $276.9M.

Source: tdlr.texas.gov ↗

Sources

Found an error? Email support@txdatacenterwatch.com with a source link.

Free weekly digest

One email a week: new filings, votes, hearings and comment deadlines in Texas data center and power projects, each with its source. No spam, unsubscribe any time.

TODO (launch): signup endpoint not connected. Submissions are not stored yet.